Enemalta said this afternoon that there was never any formal offer by Italian company ENI to invest in a gas pipeline to Malta 10 years ago.
In a statement reacting to comments made last week by former engineer John Pace, Enemalta said it never had any offer by anyone to invest in any pipeline in a way which would have been free of charge for the corporation.
The ENI report, it said, was a study which it had commissioned in January 2001 about a possible pipeline between Sicily and Malta. The study was completed in 2003.
Malta had requested consideration of the possibility of linking up with the Green Steam pipeline between Sicily and Libya, but the proposal was dropped by ENI itself for technical reasons.
The so-called financial proposal for a pipeline between Gela in Sicily and Delimara was just a reference in the annex of the report which did not lay down the price of gas and only gave an indicative formula, linked to oil prices. Important details, such as the workings of the index, were missing.
A critical aspect was the obligation which Enemalta would have had to 'take and pay', meaning that it would have had to pay for gas even if it did not use it.
The document laid down...
↧